August 13, 2026 This project is currently in the final stages of design. An updated timeline will be available once the design is complete. March 28, 2026 Hull Street, from 9th to 12th Streets, will be receiving new water and sewer lines, as well upgrades to stormwater infrastructure. This
Water Replacement – Taylor Ave and A Street
September 11, 2026 PAVING NOTICE: Taylor Ave and A Street – Monday Sept. 14th-Tuesday Sept. 15th, 2026 As the City finalizes the water replacement project on Taylor and A Streets, we will be paving/trench patch paving: Taylor Ave on Monday Sept. 14th, 2026, from 6am to 6pm. A Street
Sewer Replacement – 9th Street and 13th Street
August 13, 2026 Crews are paving the 13st Street Alley today. Once paving is complete, the major work on this section of the project will be finished, with minor testing and closing tasks remaining. The 9th and Waucoma section of this project is currently progressing well despite some
UPDATE on ODOT ADA curb ramp construction on US 30 (Oak Street and Cascade Ave)
UPDATE on ODOT ADA curb ramp construction on US 30 (Oak Street and Cascade Ave) While the contractor continues to upgrade sidewalk curb ramps in Hood River, we want to keep you informed about the progress of the project. Work is happening along U.S. 30 in Hood River which is Oak Street and
Waterfront Stormwater Relocation
January 31, 2025 Progress on construction for waterfront stormwater relocation advances on schedule without any major complications. The work on Riverside Drive is nearing completion, with work moving onto Anchor Way in the coming weeks. Additionally, in the following weeks the community can
2nd and Oak Reopens
Last week, the Hood River community celebrated the reopening of the 2nd and Oak intersection. Thank you to everyone who worked to get the traffic signal installed! Although the intersection, with new curb ramps, crosswalks and pavement, has reopened, the community can expect to see crews on-site
2nd and Oak Construction Begins – Businesses Remain Open and Accessible
Installation of the traffic light at 2nd and Oak streets in downtown Hood River begins today, February 12. Businesses will remain open and accessible during construction. The entire intersection will be closed to vehicle traffic, with detours rerouting vehicles to nearby Cascade, State, 1st and
2nd and Oak Construction Begins
May 17, 2024 The City is working hard with contractors and ODOT to be able to fully reopen the intersection before Memorial Day weekend. There are several tasks that still need to be completed before the intersection can be fully reopened. Community members and visitors in the downtown area
Montello Water and Wastewater Replacement
October 24, 2024 Intersection paving at 4th and Montello is complete. The team is currently preparing for paving east of 2nd through the dead end. Paving is expected to occur next week, weather permitting. October 11, 2024 Intersection Closure Alert On the week of October 14, the
Eugene Water/Sewer Construction
May 14, 2024 Construction on project-related water connections on 17th Street continue. Construction in this area is anticipated to continue for another two weeks. April 30, 2024 In relation to the final stages of the Eugene Street Water and Wastewater Replacement Project, construction on
Rand Cascade Intersection Progress
July 16, 2024 Installation is complete, however, there you may still encounter workers completing final tasks. May 30, 2024 Work on the Intersection at Cascade and Rand continues. View updates on the project website here:
2nd and Oak Intersection Progress
September 27, 2023 Construction on the light signal installation at 2nd and Oak has been delayed, and is expected to being in February of 2024. May 3, 2023 In preparation for the light signal installation on 2nd and Oak, NW Natural will begin moving gas lines tomorrow, Thursday, May 4th.
Construction Resumes on Prospect
May 22nd, 2023 Final paving for the Prospect Ave sewer and water replacement project is scheduled for May 24-25 for the entire project area of 2nd to 7th Streets. There will be no parking available at the time. Please make sure to follow sign instructions. This is the final step for this project,












