April 16, 2024 The construction team continues their work on-schedule. Currently, they are continuing their work on sidewalks and ADA ramps, and will then move to paving and light set-up. March 7, 2024 Construction is progressing on schedule for completion by Memorial Day. The drilled shaft
Montello Water and Wastewater Replacement
April 16, 2024 Gas relocations and preliminary work is completed. The construction team will be moving in this week to begin the work on replacing the water and sewer lines. The bulk of work is expected to take place Monday-Thursday, however there may be intermittent construction on Fridays as
Eugene Water/Sewer Construction
April 16, 2024 Construction will continue this week to wrap up the Eugene Street Water/Wastewater project with ADA ramps at 12th and Eugene, as well as some work on 17th between May and Sherman on the water system. This will completely disconnect the water services from the old lines and move
Rand Cascade Intersection Progress
March 8th, 2023 Upcoming impacts for Saturday, Mar. 9 - Saturday, Mar. 16 General traffic impacts: Construction will focus on one corner of the intersection at a time. March 7, 2024 Project continues on schedule for May 24, 2024 completion. December 14, 2023 The NE and
2nd and Oak Intersection Progress
September 27, 2023 Construction on the light signal installation at 2nd and Oak has been delayed, and is expected to being in February of 2024. May 3, 2023 In preparation for the light signal installation on 2nd and Oak, NW Natural will begin moving gas lines tomorrow, Thursday, May 4th.
Construction Resumes on Prospect
May 22nd, 2023 Final paving for the Prospect Ave sewer and water replacement project is scheduled for May 24-25 for the entire project area of 2nd to 7th Streets. There will be no parking available at the time. Please make sure to follow sign instructions. This is the final step for this project,