April 16, 2024 The construction team continues their work on-schedule. Currently, they are continuing their work on sidewalks and ADA ramps, and will then move to paving and light set-up. March 7, 2024 Construction is progressing on schedule for completion by Memorial Day. The drilled shaft
2nd and Oak Intersection Progress
September 27, 2023 Construction on the light signal installation at 2nd and Oak has been delayed, and is expected to being in February of 2024. May 3, 2023 In preparation for the light signal installation on 2nd and Oak, NW Natural will begin moving gas lines tomorrow, Thursday, May 4th.